NOTE When installing signal wiring for CAN card J3 terminals, conduit must be installed
between the device and the UPS cabinet.
4. Remove the UPS cabinet top interface conduit landing plates to drill or punch conduit holes (see Figure 40).
5. Reinstall the conduit landing plate.
6. Install conduit between the UPS and RMP II. See Figure 68 for RMP II knockout hole location.
7. Install wiring between the UPS and RMP II. See Figure 58 and Table 25 for the Powerware Hot Sync CAN
Bridge Card terminal location and wiring information, and Figure 63, Figure 64, and Table 29 for the RMP II
terminal location and wiring information.
NOTE 120 Vac for the RMP II should be supplied from the critical bus by facility planners or the
customer.
8. Install 120 Vac power wiring from the critical bus to the RMP II. See Figure 63, Figure 64, and Table 29 for
the terminal location and wiring information.
9. Close the front door and secure the latch.
10. Restart the UPS. See Chapter 7 UPS Operating Instructions for startup instructions.
Figure 63. Remote Monitor Panel II and Remote Monitor Panel II Terminal Locations