74 Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201725—Rev 15
8. Using hardware from the external wiring terminal hardware kit (see Table 14), connect phase A, B, and C
rectifier input power wiring from the utility source to the rectifier input terminals in the UPS cabinet. See
paragraph 3.2.4 UPS System Power Wiring Preparation for wiring and termination requirements.
9. If installing a UPS configured as an Input Output Module (IOM), proceed to Step 11; otherwise, proceed to
Step 10.
10. Using hardware from the external wiring terminal hardware kit (see Table 14), connect phase A, B, and C,
and Neutral (if required) bypass input power wiring from the utility source to the bypass input terminals and
neutral terminals in the ISBM section. See paragraph 3.2.4 UPS System Power Wiring Preparation for
wiring and termination requirements.
11. If wiring a distributed bypass system, proceed to Step 12; otherwise, proceed to Step 14.
12. Using hardware from the external wiring terminal hardware kit (see Table 14), connect phase A, B, and C,
and Neutral power wiring from the output and neutral terminals of each UPS unit to the customer-supplied
tie cabinet or load distribution panel. See paragraph 3.2.4 UPS System Power Wiring Preparation for wiring
and termination requirements.
13. Proceed to paragraph 4.8.3 Battery Power Wiring.
14. Using hardware from the external wiring terminal hardware kit (see Table 14), connect phase A, B, and C,
and Neutral (if required) power wiring from output terminals and neutral terminals to the critical load. See
paragraph 3.2.4 UPS System Power Wiring Preparation for wiring and termination requirements.
15. Proceed to paragraph 4.8.3 Battery Power Wiring.
UPS System Installation