ES-12B 5 Terminal Single Phase Residential Electricity
Meter - Installation and Commissioning Guide
Copyright © 2020 EDMI Europe Ltd. All rights reserved
Version / Status: 1.0
Public
PAGE 15 OF 25
Step 3: Isolate mains power supply
Isolate the mains power supply according to your company’s safety standards.
Step 4: Remove old meter
Remove the old meter. If not applicable, proceed to step 5.
Step 5: Mount the meter to the install point
The meter’s warranty may be voided unless care is taken around installing meters in
suitable positions, protected from the elements, away from water etc. Please contact
your support centre if unsure of suitability of installation position.
To mount the meter:
1. Leaving enough space between the screw head and the wall for the top keyhole (5mm), screw
the first (top) screw into the wall.
2. Hang the meter on the top screw using the keyhole.
3. Insert and tighten the remaining two screws at the meter base, under the terminal cover, to
hold the meter securely.