E F A P O W E R E V - PC - I N S T A L L A T I O N A N D U S E R M A N U A L
9 | 37
On locations with extreme weather conditions (harsh temperatures or snow) it’s recommended to provide additional
protection, either inside a building or a shelter, or providing a roof protection for the Unit. See example in Figure 6.
Figure 6 - EFAPOWER EV-PC Station with roof protection
5.1.2 SITE VERIFICATION AND INSPECTION
✓ Check if the access passages to the Public Charger Station layout site are not blocked in order to allow its
transportation;
✓ Check if the Public Charger Station layout site is compliant with the specified clearance around the cabinet;
✓ In case of installation of Central and Satellite Units, make sure that the distance between units will comply
with cable length requirement (no longer than 100 meters).