5.2.2 SURFACE PREPARATION
Each Charging Station can be mounted to the floor, or to the pavement by a proper base, or on the wall
depending on the product configuration. Check local codes to ensure compliance.
The Charging Station shall be mounted at a sufficient height from grade, such that the height of the storage
means for the coupling device, is located between 600 mm (24 inches) and 1.2 m (4 feet) from grade.
5.2.3 RESOURCES FOR INSTALLATION
For the installation of EFAPOWER EV-PC Station, the following items will be needed:
Fasteners:
Mounting on the Wall
▪ Concrete wall: 4 (four) anchors, M5 – length must comply with local codes – with matching nuts and washers,
or
▪ Drywall: 2 (two) anchors (13/64’’ dia. (M5) lag screws ) in studs and 2 (two) drywall anchors heavy-duty
Anchoring to the Floor
▪ 4 (four) screws M8, with matching nuts and washers
End terminals for input wiring by Unit:
▪ CE or GB marked units: 5 (five) end terminals for cable according to Table 5 or according to local codes
(3phases + neutral + protective ground)
Table 5 - Input lines –cross-section range
* These cross-sections are applied to cooper cable length up
to 50m. For longer distances, contact the manufacturer.