E F A P O W E R E V - PC - I N S T A L L A T I O N A N D U S E R M A N U A L
13 | 37
Connection between Central and Satellite Units only communications (if applicable):
Ethernet patch cable STP CAT5e TIA/EIA-568B
Tools:
Screwdriver - for fixing the Unit on the wall
13mm socket and wrench - for fixing the Unit to the floor
Crimping tool - for power and earth cables
Torque screwdriver with flat blade - for input terminal blocks
5.2.4 SITE VERIFICATION AND INSPECTION
Check if Public Charger has the appropriate upstream protection depending on the configuration.
Check if the surface where the Public Charging Station will be placed is leveled as specified.