8
Motor set
Arm
Φ50mm
Landing gear
Spraying tank
Centrifugal nozzle
Cabin
Front cover
Camera
Rear cover
Landing gear crossbar
Arm buckle
Radar
Antenna
RTK
Flight control
Receiver
Level gauge
Impeller pump
Ultrasonic flow meter
Pre-flight Preparation
Inspection
Check whether the components are in good condition, especially the landing gear , the
internal flight control and flow meter interface etc..
Check the identification on the motors and propellers to ensure that the installation order is
correct (CW—M2/M4, CCW—M1/M3).
Check that all pins are not skewed and that the cables are properly connected.
Check whether the arm and cover is locked, and whether the nozzle is installed firmly.
After a overall inspection, level the motors, then unfold paddles and ready for testing.
Smart Battery
Installation
The smart battery can be installed directly, insert battery until hearing a clicking sound, then lock