PRODUCT MAINTENANCE
06/2020 51 NP-DK50 2V 50, 2x2V 110-A-5_06-2020-MD
PROCESS:
Jumper installation (A-B-C-D process)
Disconnect the product from the mains by pulling the plug out of the socket.
Remove the cover on the electrical panel (on the compressor).
The jumper is not in the terminal strip – A.
Lift up the fuse cover – B.
Insert the jumper into the terminal strip – C.
Close the fuse cover – D.
Reinstall the cover on the electrical panel.
Connect the device to the electrical mains.
Activate the compressor by turning on the switch on the pressure switch.
Fig. 19: DK50 2V/50
230 V
B
C
D