Liquiphant FTL51B Installation
Endress+Hauser 13
5.1.3 Avoiding buildup
A0033239
 10 Installation examples for a highly viscous process medium
Use short installation sockets to ensure that the turning fork can project freely into the
vessel.
Install preferably flush-mounted on vessels or in pipes.
Leave sufficient distance between the buildup expected on the tank wall and the tuning
fork.
5.1.4 Take clearance into consideration
A0033236
 11 Take clearance into consideration
Allow sufficient space outside the tank for mounting, connection and settings involving
the electronic insert.