4.0 4.0 InstallationInstallation
4.1 4.1 Installation PreparationInstallation Preparation
When selecting an installation location, ensure that all of the
following conditions are met before proceeding�
4.1.1 4.1.1 Elevated Operating Ambient TemperatureElevated Operating Ambient Temperature
If you install the panel in a closed or multi-unit rack assembly, the
operating ambient temperature of the rack environment may be
greater than room ambient� Therefore, take care to install the
equipment in an environment compatible with the maximum ambient
temperature (TMA)�
4.1.2 4.1.2 Reduced Air FlowReduced Air Flow
Installation of the equipment in a rack should be such that the
amount of air ow required for safe operation of the equipment is not 
compromised�
4.1.3 4.1.3 Mechanical LoadingMechanical Loading
Mounting of the equipment in the rack should be such that a
hazardous condition is not achieved due to uneven mechanical
loading�
4.1.4 4.1.4 Circuit OverloadingCircuit Overloading
Give consideration to the connection of the equipment to the
supply circuit and the e󰀨ect that overloading of the circuits might 
have on overcurrent protection and supply wiring� Use appropriate
consideration for equipment nameplate ratings when addressing this
concern
4.1.5 4.1.5 Reliable EarthingReliable Earthing
Maintain reliable earthing of rack-mounted equipment� Pay particular
attention to supply connections other than direct connections to the
branch circuit (e�g�, use of power strips)�
4.1.6 4.1.6 Disconnect DeviceDisconnect Device
A readily accessible disconnect device must be incorporated in the
building installation wiring�