Cleaning and maintenance
10/2013 1014906-00 Operating instructions – 37/76
In addition to the maintenance plan on page 36, the following items should be
checked to ensure safe operation and use of your tanning system.
Component Interval
1)
Activity
250 h / 3 months
500 h / 6 months
2500 h / 1 year
5000 h / 5 years
10000 h / 10 years
1 Springs X Inspect and replace as necessary
Springs X Replace
2 Bolts and fasteners of the canopy
hinge mechanism
X Inspect and replace as necessary
Bolts and fasteners of the canopy lift
mechanism
X Inspect and replace as necessary
Bolts and fasteners of the canopy
hinge/lift mechanism
X Replace
3 Bolts and fasteners of the base/tank
hinge/lift mechanism
X Inspect and replace as necessary
Bolts and fasteners of the base/tank
hinge/lift mechanism
X Replace
4 Cylinders X Inspect and replace as necessary
Cylinders X Replace
5 Chassis and associated fasteners X Inspect and replace as necessary
Chassis and associated fasteners X Replace
6 Wiring and associated plugs / termi-
nal connections
X Inspect and replace as necessary
7 Acrylic panels
2)
X Inspect and replace as necessary
Acrylic panels
2)
X Replace
8 Acrylic support(s) X Inspect and replace as necessary
Acrylic support(s) X Replace
9 High pressure filter glass X Inspect and replace as necessary
High pressure filter glass X Replace
10 High pressure lamp holder X Inspect and replace as necessary
High pressure lamp holder X Replace
1) Interval must be repeated after each inspection or replacement
(i.e. 1st: 3 months, 2nd: 6 months, 3rd: 9 months, etc.)
2) The schedule for acrylic replacement listed refers only to the condition of
the acrylic relating to safety and does not address the efficacy of UV
transmission.