NOTICE:
Make sure that the rotation of the impeller is correct. For more information, see Check the
impeller rotation.
1. Remove the fuses or open the circuit breaker, and check that the impeller can be
rotated freely.
2. Conduct insulation test phase to ground. To pass, the value must exceed 5 megohms.
3. Check that the monitoring equipment works.
4. Start the pump.
Operation