EasyManua.ls Logo

GE 469

GE 469
307 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
GE Power Management 469 Motor Management Relay 7-13
7 TESTING 7.3 ADDITIONAL FUNCTIONAL TESTING
7
7.3.5 SHORT CIRCUIT TEST
The 469 specification for short circuit timing is +50 ms. The pickup accuracy is as per the phase current inputs.
Perform the steps below to verify the performance of the short circuit element.
1. Alter the following setpoints:
S2 SYSTEM SETUP\CURRENT SENSING\PHASE CT PRIMARY: 1000
S6 CURRENT ELEMENTS\SHORT CIRCUIT TRIP\SHORT CIRCUIT TRIP: On
S6 CURRENT ELEMENTS\SHORT CIRCUIT TRIP\ASSIGN TRIP RELAYS: Trip
S6 CURRENT ELEMENTS\SHORT CIRCUIT TRIP\SHORT CIRCUIT TRIP PICKUP: 5.0
×
CT
S6 CURRENT ELEMENTS\SHORT CIRCUIT TRIP\INTENTIONAL S/C DELAY: 0
2. Inject current as per the table below, resetting the unit after each trip by pressing the key, and verify
timing accuracy. Pre-trip values may be viewed by pressing after each trip.
Table 7–18: SHORT CIRCUIT TIMING
INJECTED CURRENT EXPECTED TIME
TO TRIP
MEASURED TIME
TO TRIP
5 A UNIT 1 A UNIT
30 A 6 A < 50 ms
40 A 8 A < 50 ms
50 A 10 A < 50 ms
RESET
NEXT

Table of Contents

Other manuals for GE 469

Related product manuals