INSTALLATION
22 / 146 OI 250 (EN) REV7 /REV7
Checklist for Installation and Commissioning
Circuit Breaker Data
Type & Serial No.:
Customer:
Station:
Installation
No. Operation to Be Performed Section
1 Safety instructions have been carefully read and are under-
stood
2.1
2 Materials provided by station checked for completeness A2
3 Shipment checked for completeness and lack of damage 6.4
4 Component serial numbers checked for agreement 6.4
5 SF
6
shipping pressure in each pole column checked 6.4.1
6 Lattice supports mounted 6.5
7 Connecting brackets mounted 6.6
8 Density monitor and filler block mounted on lattice supports 6.7
9 Mechanisms mounted on lattice supports 6.8
10 Pole columns installed 6.9
12 Drive rod connected to drive lever 6.9.3
13 Drive rod adjusted to reduce clearance and pole columns
completely tightened
6.9.3
14 Transport lock removed from operating mechanism 6.8
15 High voltage terminal pads mounted 6.10
16 Lattice supports grounded 6.12