CONFIGURATION & FIELD CALIBRATION
To accept extended period option:
Press and hold YES
, as indicated on the
bottom line of the display, and the instrument warm-
up continues.
Note: When the extended period option expires,
the user will be forced to switch the instrument
OFF.
To reject extended period option:
Press and hold NO
, as indicated on the bottom
line of the display. The screen shown in Fig. 1.13
is displayed.
Fig. 1.13 Switch OFF
Press and hold both the LH (INVERT) button
and the RH (PUMP) button simultaneously to
proceed with the switch-off sequence.