46
13. Point Projection
Point projection is used for projecting a point to an established baseline. By measuring a
point, its offset to start point, the horizontal distance and vertical distance between the
point and baseline can be calculated. the figure is shown as follow.
13.1 Define Baseline
Procedure of defining baseline
1. Select the menu item 2 to define a baseline
2. Measure the start point of the baseline
eP
Pt’
Pt
sP
VD
HD
oSD
Survey (Height)
1.I.H. &T.H.
2.Set baseline
3.Point project
Pt.project(Begin)
Vz: 80°00' 13"
HR: 340°56' 50"
SD: 4.890m
HD: 4.831
Meas T.H. Mode Enter

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GPI GPI-122 and is the answer not in the manual?

GPI GPI-122 Specifications

General IconGeneral
BrandGPI
ModelGPI-122
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals