Installation
88
No.
Name
Remarks
1
Leaving Water Pipe
1″Male BSP
2
Returning Water Pipe
1″Male BSP
3
Gas-side Pipe
5/8
GRS-CQ8.0/10Pd/NaE-K, GRS-CQ12/14/16Pd/NaE-K
GRS-CQ12/14/16Pd/NaE-M
4
Liquid-side Pipe
3/8
GRS-CQ8.0/10Pd/NaE-K, GRS-CQ12/14/16Pd/NaE-K
GRS-CQ12/14/16Pd/NaE-M
4.7 Installation Clearance Data
(1) Indoor unit shall be vertically mounted on the wall of the room with expansion bolt.
(2) Keep the indoor unit away from heat sources like heat sink and so on in the room as much as
possible.
(3) Keep the indoor unit as close as possible to outdoor unit. Level distance between connection
pipes cannot exceed 30m (8.0~14kW) and vertical distance cannot exceed 15m (8.0~14kW).
4.8 Installation of Water Tank
(1) Installation measure
The insulated water tank should be installed and keep levelly within 5m and vertically within 3m from
the inner unit. It can be installed in the room.
Standing water tank must be installed vertically with the bottom on the ground, never
suspended.Installation place must be firm enough and the water tank should be fixed on the wall with
bolts to avoid vibration, as shown in the following figure. Weight capacity of water tank during installation
should also be considered.