Debugging 7
1. Close the DC switch on the inverter. As long as the input DC voltage is greater than
MOV,the inverter display will show the following information: No mains connection error,the in-
verter LED will turn red.
If other information is displayed, please refer to Chapter 13.If you encounter any problems dur-
ing the debugging process and cannot solve it,please contact customer service.
2. Close the circuit breaker or switch between the inverter and the grid, the inverter will start a
countdown to the self-check,and after the self-check is normal,it will be connected to the grid.
3.In normal operation,the leaves of the inverter indicator window will turn green.
4. Finish debugging.