2017_E_TYPE-HL.doc Page 22 of 55 24-Oct-2017
Note:
a. Gaskets are not required between the stack flanges. However, if sealant is available, it
is recommended that a bead be placed on a flange face before each section is bolted
together.
b. A barometric damper is required if the stack height exceeds 27' (or 1.5 times the
standard stack height).
c. Standard stack installation is through the roof. A through the wall installation may be
ordered as a special option.
3.8.3 Procedure
1. Unload the oven shipment. Remove the protective packaging and unpack the
components.
2. The oxidizer chamber on some larger ovens is shipped separately. Oxidizer chamber
installation is via a bolt on assembly as depicted in Figure 3.1.
3. Set the oven in assigned location. Use the stack lifting lugs provided and set the stack in
the marked stack base location. Special stack installation instructions for ovens with
heavy-duty oxidizers are depicted in Figure 3.2.
Note: When locating the base stack, locate the thermocouple ports to the rear.
4. Connect water, fuel and electrical supplies.
5. The cart extensions should be hooked on the oven and care should be taken to ensure that
they sit on a level plane.