Procedure
Step 1 Install the server.
At least two people are required to move the device. Otherwise, personal injury or
device damage may occur.
1. Lift the server, place it on guide rails, and slide it into the chassis. At least two
people are required to move the server. See (1) in Figure 7-8.
2. Align the mounting ears on both sides of the server with the mounting bars
and tighten the captive screws on the mounting ears. See (2) in Figure 7-8.
Figure 7-8 Installing the server
Step 2 Connect the power cables to the PSUs.
For details, see 7.2.6.7 Connecting PSU Cables.
Step 3 Connect a network cable, a VGA cable, and USB devices as required.
Step 4 Power on the server.
For details, see 7.3.1 Power-On Procedure.
Step 5 Check indicator status.
For details, see 2.1.2 Indicators and Buttons.
----End