2 Cabinet Power Cable Connections (DPD63-4-8 PDU)
DPD63-4-8 PDU
a
Remove the front panel of the DC PDU prior to installing power cables. After installing the power cables, restore
the front panel of the DC PDU to the original position.
By default two-in-one copper fittings have been installed on NEG(-) and RTN(+) terminals of the PDU before the
delivery. Based on the site survey result, determine whether the two-in-one copper fittings pre-installed on NEG(-)
terminals need to be replaced with four-in-one copper fittings and whether additional four-in-one copper fittings
need to be installed on the RTN(+) terminals in the middle of the PDU.
NOTE
DC PDU (with the front panel installed)
DC PDU (with the front panel removed)
Two-in-one copper fitting (left)
NEG (-)
Two-in-one copper fitting (right)
NEG (-)
Two-in-one copper fitting (middle)
RTN (+)
Power output area (A) Power output area (B)
Power input area (A) Power input area (B)
A1/A2 (-) A3/A4 (-)
B1/B2 (-) B3/B4 (-)
A1/A2
(+)
A3/A4
(+)
B1/B2
(+)
B3/B4
(+)
Do not install any copper fitting in the power output areas of the DC PDU. If copper fittings are required, install
them only in the power input areas of the DC PDU.
DANGER
Power switch area (A)
Power switch area (B)