Figure 8-22 Installing an MCB
Step 5 Install all other MCBs in the same way according to the capacity expansion principles.
The number of MCBs to be installed vary depending on site requirements.
Each reserved label code corresponds to one 1P MCB. A 3P MCB takes up three label codes.
Step 6 Reinstall the front panel.
Step 7 Tap Maint. on the System Info. screen to enter the Expansion Settings screen.
Figure 8-23 Capacity expansion settings
Second method for setting capacity expansion: Turn on the MCB. The dialog box for setting capacity
expansion is displayed on the MDU. If you do not want to set capacity expansion, cancel the displayed
dialog box for setting capacity expansion for three consecutive times to cancel capacity expansion
settings.
Step 8 Tap Add to set the MCB quantity, phases, and capacity.