This table may not list some tools required at specific sites. Site installation personnel and technical 
support personnel should prepare tools based on site requirements. 
 
Prepare firestop putty for sealing cable holes after cable connection. Huawei does not provide the 
firestop putty. The customer needs to purchase it. 
5.2.3 Checking Personnel Requirements 
Construction personnel must have basic knowledge of safe operation, be trained to master 
correct operation methods, and have the appropriate job qualifications. 
The owner should pay attention to the following items when organizing the construction 
personnel to carry out construction work: 
 
Construction personnel have been trained and qualified by Huawei to master methods for 
system installation and commissioning, and have obtained work permits before they 
begin to install and commission equipment. 
 
The number of construction personnel depends on the project progress and the 
installation environment. 
 
Construction personnel have read through the safety precautions and related product 
documents before they begin work. 
5.3 Installing the PDC 
Prerequisites 
 
The installation environment has been checked with expected results. 
 
The site has been closed off, and notices have been posted. 
 
The PDC has been unpacked and inspected, and no problems were found. 
 
You have obtained the tools and meters required for the installation. 
 
Installation personnel must be qualified and certified. Power distribution equipment 
operators must hold a primary electrician certificate or higher. 
Context 
 
A modular precision PDC can be installed on a concrete floor or an ESD floor. 
 
A modular precision PDC can be deployed separately or combined with another cabinet.   
 
As the onsite conditions may vary, the following steps are for reference only. Onsite installation 
personnel and technical engineers can decide whether to perform the steps based on the actual situation.   
5.3.1 Moving the PDC 
Context