Figure 3-21 Installing leveling feet
Step 2 Secure the IP21 component to the top of each cabinet.
Figure 3-22 Installing an IP21 component
----End
3.5.5 (Optional) Installing a Water Sensor
Prerequisites
A water sensor is provided.
Procedure
Step 1 Install a water sensor at the bottom left of the cabinet and secure it with a cable tie.
Step 2 Connect the signal cable of the water sensor to the WATER terminal on the BCU.