Figure 76. Reconnecting the signal cable and the power cable
3. Replace the air baffles. For instructions, see Replacing the air baffle (www.ibm.com/support/
knowledgecenter/POWER9/p9haj/p9haj_922_airbafflereplace.htm).
Preparing the 5105-22E, 9008-22L, 9009-22A, 9009-22G, or 9223-22H system for
operation after removing and replacing the drive backplane signal cable
To prepare the system for operation after removing and replacing a drive backplane signal cable,
complete the steps in this procedure.
Procedure
1. Slide the service access cover (A) onto the system unit.
2. Close the release latch (B) by pushing it in the direction shown.