Three-phase Grid-tied Solar Inverter Installation
16
(6) The installation environment temperature is - 25 ℃ ~ 60 ℃;
(7) The installation site should be far away from the electronic equipment with strong
electromagnetic interference;
(8) The installation site should be fixed and solid object surface, such as wall, metal support, etc;
(9) The installation position shall ensure the reliable grounding of the inverter, and the grounding
metal conductor material shall be consistent with the reserved grounding metal material of the
inverter.
4.3 Space requirements
(1) The height of installation position shall ensure that the line of sight and LED display light are on
the same horizontal plane, so as to check the inverter status conveniently .
Fig 4.3 Optimum installation height area
(2) There is enough reserved space around the installation site to facilitate the disassembly and
assembly of inverter and air convection. As shown in Fig 4.3.
Fig 4.4 Installation spacing of inverter