SECTION 3 - COMPONENT SERVICING
3121741 – JLG Lift – 3-7
3.5 PLATFORM INSTALLATION
Ecolift50/70
1. Remove the four bolts, nuts and washers secur-
ing the floor pan to the platform assembly.
Remove floor pan.
2. Remove the six bolts, nuts and washers securing
the platform assembly to the mast assembly.
3. Loosen the bolt and nuts on the bottom rail
cross-member to allow the platform rails to clear
the mast mounting sockets.
4. With the aid of an assistant, remove platform
from mast by pulling each rail out from it’s mast
socket then lifting the platform off and setting
aside.
NOTE: When assembling apply anti-seize compound to the
platform rail attach bolts/nuts (item 4).
830P
1. Release platform latch lock pin and swing the
front of the platform up until it can be supported
by the gas strut catch mechanism.
2. Support platform from the top rails using suit-
able overhead lifting equipment. Lift platform
enough to take the weight of the platform off of
the gas strut.
3. Unbolt and remove the gas strut.
4. Let the front of the platform down carefully until
level. Now move the lifting straps to the center
of the platform rails to support the platform.
5. Remove the platform to mast mounting bolts,
washers and nuts.
6. Carefully lift the platform off the machine and
set aside.
Figure 3-11. Platform Installation - Ecolift50 and 70
1. Platform Assembly
2. Floor Pan Assembly
3. Floor Pan Mounting Bolts and Washers
4. Platform to Mast Bolts and Washers
Figure 3-12. Platform Installation - 830P
1. Platform Assembly
2. Gas Strut w/Catch Mechanism
3. Platform to Mast Bolts and
Washers
Go to Discount-Equipment.com to order your parts