PTX10000 Site Preparation Overview
IN THIS SECTION
PTX10000 Site Preparation Checklist | 149
PTX10000 Environmental Requirements and Specifications | 151
PTX10000 General Site Guidelines | 152
PTX10000 Site Electrical Wiring Guidelines | 153
PTX10000 Rack Requirements | 155
PTX10000 Clearance Requirements for Airflow and Hardware Maintenance | 156
PTX10008 Chassis Physical Specifications | 159
PTX10016 Chassis Physical Specifications | 161
The following sections describe the guidelines, the specifications, and the requirements to prepare the
site for installing a PTX10008 or a PTX10016 router.
PTX10000 Site Preparation Checklist
The checklist in Table 48 on page 149 summarizes the tasks you need to perform when preparing a site for
a PTX10008 or a PTX10016 installation.
Table 48: Site Preparation Checklist
DatePerformed ByFor More InformationItem or Task
Environment
“PTX10000 Environmental Requirements and Specifications”
on page 151
Verify that
environmental
factors such as
temperature
and humidity
do not exceed
router
tolerances.
149