III - 12
Operation
3.10 Work input
3.10.1 Preparing for the loading process
Adjust to the desired cutter number and therefore the
cutting length see Page III - 7/8
Adjust the pick-up working height: see Page III - 6
Normal position of baffle plate: see Page III - 6
The swathe should be uniform and loose.
3.10.2 The loading process
3.10.2.1 General information on loading
Avoid pressing too hard. Switch on the advance in time
or, during loading, switch on the „moist“ automatic
state.
When loading, adjust the speed of travel to the
thickness of the swathe, type of loading material and
the number of cutters installed.
a)
3.10.2.2 For the electromagnetic operator-friendly
control unit without automatic loader
When starting the loading process, switch on the
hydraulic oil circulation on the tractor and arrest the
switch lever.
Switch the pick-up switch to "Lower".
The pick-up can be run in this position during the whole of
the loading process so that the pick-up is able to
accomodate itself to the ground.
Switch on the power take-off shaft and start the loading
process.
When starting the loading procedure, switch on the
scraper-floor advance when the loading material has
reached approx. 3/4 of the total height in order to
prevent the pile from tipping over.
As loading continues, switch on the scraper floor when
the loading height has been reached or if the loading
unit runs unevenly because the loading material is
heavy.