6 Commissioning/Start-up/Shutdown
30 of 60
Multi Eco
6 Commissioning/Start-up/Shutdown
6.1 Commissioning/Start-up
6.1.1 Prerequisites for commissioning/start-up
Before commissioning/starting up the pump set, make sure that the following
conditions are met:
▪ The pump set has been properly connected to the electric power supply and is
equipped with all protection devices.
▪ The pump has been primed with the fluid to be handled.
▪ The direction of rotation has been checked.
▪ All auxiliary connections required are connected and operational.
▪ After prolonged shutdown of the pump (set), the activities described in
(ðSection6.4,Page35) have been carried out.
6.1.2 Priming the pump
1. Unscrew the filler screw.
2. Fill in the fluid to be handled (min. 1.8 l)
3. Screw the filler screw back in and tighten to a torque of 10 Nm (max.).