6 Commissioning/Start-up/Shutdown
35 of 60
Multi Eco
If the pump set is to be stored temporarily, only preserve the wetted components
made of low-alloy materials. Commercially available preservatives (food-approved, if
required) can be used for this purpose. Observe the manufacturer's instructions for
application/removal.
Observe any additional instructions and information provided. (ðSection3,Page11)
6.4 Returning to service
For returning the equipment to service, observe the sections on commissioning/start-
up (ðSection6.1,Page30) and the operating limits.
In addition, carry out all servicing/maintenance operations before returning the
pump (set) to service. (ðSection7,Page36)
WARNING
Failure to re-install or re-activate protective devices
Risk of personal injury from moving parts or escaping fluid!
▷ As soon as the work is complete, re-install and/or re-activate any safety-relevant
and protective devices.
NOTE
If the pump has been out of service for more than one year, replace all elastomer
seals.