EasyManua.ls Logo

Lenze E84DGFCRFNP - Commissioning

Lenze E84DGFCRFNP
93 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Lenze · Inverter Drive 8400 motec (PROFINET® option) · DMS 5.0 EN · 02/2019 · TD23 25
6 Commissioning
6.1 Before initial switch-on
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
6 Commissioning
During commissioning, system-related data such as motor parameters, operating parameters,
responses, and parameters for fieldbus communication are defined for the inverter. For Lenze
devices, this is done via the codes.
The codes of the inverter and communication are saved non-volatilely as a data set in the memory
module.
In addition, there are codes for diagnosing and monitoring the stations.
Parameter reference
( 75)
The data from the inverter or the memory module can only be read with the main voltage supply
(400/500 V AC).
For commissioning with 24 V DC, only the data of the digital and analog inputs in the last two data
words are valid and readable (see Process input data AI/DI (Slot2)
( 44)).
6.1 Before initial switch-on
Stop!
Before switching on the inverter for the first time, check the entire wiring with regard to
completeness, short circuit, and earth fault.

Table of Contents

Related product manuals