Installation
1. Position the radiator assembly in the carrier using a
lifting device and secure the radiator to the mount
bracket with the hardware.
2. Secure the support plates to each side of the radiator
using a bolt.
3. Attach the fan guard to the shroud using the hardware.
4. Connect all hoses to the radiator assembly as tagged
during removal.
5. Ensure the drain cock is closed.
6. Service the engine coolant system, transmission oil
system, and the hydraulic system as necessary. Start
the engine, operate all systems and check for leaks.
FIGURE 7-10
1
2
3
8089-2
4
Item Description
1 Radiator Assembly
2Drain Cock
3 Fan Guard
4 Overflow Tank
Reference Only

Table of Contents

Other manuals for Manitowoc Grove RT530E-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove RT530E-2 and is the answer not in the manual?

Manitowoc Grove RT530E-2 Specifications

General IconGeneral
BrandManitowoc
ModelGrove RT530E-2
CategoryConstruction Equipment
LanguageEnglish

Related product manuals