EasyManua.ls Logo

Maple Armor FW106 - System Checkout; Before Turning the Power ON; Power-up Procedure

Maple Armor FW106
73 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
InstallationandOperationManual
36

SystemCheckout
Thefollowingaretherecommendedstepsthatshouldbefollowedbeforeandduringthepoweringupofthe
FW106/FW106C.
BeforeTurningthePowerON
1.Topreventsparking,DONOTconnectthebatteryfirst.Connectingthebatteriesshouldonlybedoneoncethe
systemhasbeenpoweredfromthemainACSupply.
2.Checkallfield(external)wiringforopens,shorts,andground.
3.Checkthatallinterconnectioncablesaresecureandthatall connectors
arepluggedinproperly.
4.Checkallswitchesforpropersetting.
5.ChecktheACpowerwiringforproperconnection.Observe/checkslideswitchposition.
6.ClosethefrontcoverplatebeforepoweringthesystemfrommainACsupply.
PowerupProcedure
1.AftercompletingBeforeTurningthePowerONprocedures,powerupthepanel.
ThegreenACONLEDshouldilluminate.
2.Sincethebatteriesarenotconnected ,theBatteryTroubleLEDshouldilluminate,the
TroubleLEDshouldflashandtheTroubleRelay(onthemainboard)willbeactive.
3.Connect
thebatterieswhileobservingcorrectpolarity;theredwireispositive(+)andblackwireisnegative
().
4.AllindicatorsshouldextinguishexceptfornormalpowerACONgreenLED.


Table of Contents

Related product manuals