Maintenance
Preventive Maintenance
During Commissioning
• Torque all power connections during commissioning, including pre-
wired equipment.
• Check all control wiring for loose connections.
• If fans are installed, check for proper operation.
One Month After Commissioning
• Re-torque all power connections, including pre-wired equipment.
• If fans are installed, check for proper operation.
After First Month of Operation
• Re-torque all power connections, including pre-wired equipment
annually.
• Clean accumulated dust with clean compressed air.
• Inspect cooling fans, if present, every three months.
• Clean or replace air vent filters every three months.