During filling, it might not be possible to remove all air in the 
system. Remaining air will be removed through the automatic 
air purge valves during the first operating hours of the system. 
Topping up the water afterwards might be required.
■  The water pressure indicated on the manometer will vary 
    depending on the water temperature (higher pressure at 
    higher water temperature).
    However, at all times water pressure should remain 
    above 0.3 bar to avoid air entering the circuit.
■  The unit might drain-off too much water through the 
    pressure relief valve.
■  Water quality must be according to "Safe Drinking water
    Act "
The ground fault circuit interrupter must be a high- speed 
type breaker of 30 mA (<0.1 s).
The complete water circuit including all piping, must be insulated to 
prevent condensation during cooling operation and reduction of the 
heating and cooling capacity as well as prevention of freezing of the 
outside water piping during winter. The thickness of the sealing 
materials must be at least 13 mm with λ= 0.039 W/mK in order to 
prevent freezing on the outside water piping.
If the temperature is higher than 30°C and the humidity is higher than 
RH 80%, then the thickness of the sealing materials should be at 
least 20 mm in order to avoid condensation on the surface of the seal.
■  This unit is equipped with an inverter. Installing a phase advancing
    capacitor not only will reduce the power factor improvement effect, 
    but also may cause abnormal heating of the capacitor due to high-
    frequency waves. Never install a phase advancing capacitor as it 
    could lead to an accident.
9.6.1 Precautions on electrical wiring work
■  Fix cables so that cables do not make contact with the pipes 
    (especially on the high pressure side).
■  Secure the electrical wiring with cable ties as shown in figure 
    so that it does not come in contact with the piping, particularly on
    the high-pressure side.
■  Make sure no external pressure is applied to the terminal 
    connectors.
■  When installing the ground fault circuit interrupter make sure 
    that it is compatible with the inverter (resistant to high frequency 
    electrical noise) to avoid unnecessary opening of the ground fault 
    circuit interrupter.
9.6.2 Overview
The illustration below gives an overview of the required field wiring 
between several parts of the installation.  Refer also to "8 Typical 
application examples".
Be aware of the hygroscopic property of glycol. It absorbs 
moisture from the environment.
Leaving the cap off the glycol container causes the 
concentration of water to increase. The glycol concentration 
is then lower and the water could freeze. 
Preventive actions must be taken to ensure minimal 
exposure of the glycol to air.
Also refer to "10.3 Pre-operation checks/Checks before initial 
start-up"
1.  Connect the water supply to the fill valve and open the valve.
2.  Make sure the automatic air purge valve is open (at least 2 turns).
3.  Fill with water until the manometer indicates a pressure of 
     approximately 2.0 bar. Remove air in the circuit as much as 
     possible using the air purge valves. Air present in the water circuit 
     might cause malfunctioning of the backup heater.
■  Be sure to use a dedicated power supply. Never use a
    power supply shared by another appliance.
■  Be sure to establish a ground. Do not ground the unit to 
    a utility pipe, surge protector, or telephone ground.
    Incomplete grounding may cause electrical shock.
■  Be sure to install a ground fault circuit interrupter (30 mA).
    Failure to do so may cause electrical shock.
■  Be sure to install the required fuses or circuit breakers.
NOTE
NOTE
■  
■  
■  
■  A main switch or other means of disconnection, having a c
    ontact separation in all poles, must be incorporated in the fixed 
    wiring in accordance with relevant local laws and regulations.
■  Switch off the power supply before making any
    connections.
■  Use only copper wires.
■  Never squeeze bundled cables and make sure they do not 
    come in contact with the piping and sharp edges. Make sure no 
    external pressure is applied to the terminal connections.
■  All field wiring and components must be installed by a
    licensed electrician and must comply with relevant local
    laws and regulations.
■  The field wiring must be carried out in accordance with the
    wiring diagram supplied with the unit and the instructions
    given below.
NOTE
WARNING
Do not fasten the black 
plastic cover on the vent 
valve at the topside of the 
unit when the system is 
running. Open air purge 
valve, turn anticlockWise at 
least 2 full turns to release 
air from the system.
29