4-2 Preparing the game for operation
If installing a single player FINAL LAP 3 unit, check the following:
a.
Be sure all power is disconnected before making any adjustments.
b. Remove the monitor AC power cord, and plug it into the power supply.
C
.
Note the position of the Link PCB Switch located in the recessed metal box
opposite the power supply on the lower back panel of each Monitor Cabinet.
d.
Each FINAL LAP 3 is shipped with the connector switch set for a single
cabinet operation, and should have the slide switch set in the “OUT” position.
Check to make sure it is set to “OUT” (see below).
Illustration 4-2, LINK CONNECTION
-
ONE CABINET
4-3 Connecting two (2) or more FINAL LAP 3s
Up to eight (8) FINAL LAP 3s can be interconnected (linked) to allow up to eight
(8) players to participate in the same race. When linking two or more games, the
following conditions must be met:
a.
Each FINAL LAP 3 game should be connected to a separate power outlet.
b.
Game difficulty and lap settings must be the same on all monitors in the
linked group. (Ref. 5-3-(2))
c.
All connecting slide switches should be set to the “IN” setting.
d.
Install the link cables between the FINAL LAP 3s by connecting an “OUT”
from one Monitor Cabinet to an “IN” of another game per the following
diagrams. Be sure to seat each plug solidly in its jack.
e.
Perform the self-test by turning the power on to each game. Make sure that
the connections are properly made between games. (Ref. 5-3-1, Self-Test)