general information
1.2 installation checklist
GAS FIREPLACE INSTALLATION CHECKLIST
This checklist is a reference tool only. It is not intended as a subs�tute for the installa�on instruc�ons.
Wolf Steel Ltd. recommends photographs of the various stages of construcon be led along with a copy of this completed form.
Is the replace level and secured?
IF NOT, PLEASE EXPLAIN WHY?
Are the factory supplied non-combusble materials installed?
Is the exterior wall insulated and dry-walled?
Are the clearances to combusbles maintained?
Are the logs/media installed as instructed?
Are the accessories installed as instructed?
Is the glass door properly sealed and unobstructed?
Is the safety barrier installed and secure?
Are all required accessories installed (i.e. door trims)?
Is the venng conguraon within the parameters?
Has the venng been sealed with the appropriate sealant?
Is the venng supported and secured?
Are all clearances to combusbles maintained?
Are the appropriate restops and shields properly installed?
Is the terminal, level, secured and sealed?
Gas and Electrical
Was the replace converted to propane?
Was the appropriate supply pressure veried?
Were all gas connecons leak tested?
Is the 110 VAC supply connecon to the replace compliant?
Are all electrical wires protected from damage?
Finishing
Non-combusble materials used as per instrucons?
Enclosure instrucons forwarded to builder/nisher?
Minimum enclosure dimensions compliant?
Combusble Mantle Clearances compliant?
Commissioning
Was the replace test red and all operaon veried?
Safety and lighng instrucons reviewed with the Customer?
Operang Instrucon Manual le with the Customer?