Transportation, installation and storage
K-MT1-8_EN_08—2014 21
► Secure the cardboard box or pallet
on the lifting or forklift truck against
sliding movements.
► Transport the dryer to its installation
site.
► Remove the packaging of the dryer.
K-MT 1-4: Dryer in a cardboard box
K-MT 6-8: Dryer on transportation pallet
Note the weight of the dryer!
Depending on its size, the dryer may weigh up to approx. 80 kg. Take this
into account with regard to the following work steps!
► Carefully place the dryer in an upright position.
► Place the dryer at its installation site.
Anchor dryer to the floor
The upright stand profiles of the dryer
are provided with pre-drilled anchorage
bores (see figure).
► Use suitable attachment material
to anchor the dryer to the floor.
► In the case of vibrating floors:
place the dryer on suitable
vibration dampers.
Bores on the stand profiles
Mount dryer on the wall
The stand profiles can be rotated by 90° towards the rear side of the dryer and
secured in this position (see arrow in above figure).
► Remove the screws at the muffler and the stand profiles. Rotate the stand
profiles by 90° until the auxiliary holes for the securing screws and the muffler
are aligned with each other. Retighten the screws securing the stand profile
and the muffler.
► Use suitable attachment material of sufficient carrying force to anchor the
dryer to the wall.