Installation 
K-MT1-8_EN_08—2014  23 
Installation  
 
 
Only authorized and qualified specialist personnel may carry out work on 
pipes and electrical systems.  
As soon as the dryer has been set up at its installation location, you can install 
the compressed air infeed and outlet lines make the electrical connections.   
 
Preconditions for installation  
For a correct installation the following preconditions must be met on the part of 
the owner.  
  Connections and lines for the infeed and outfeed of compressed air must be 
provided.  
  A compressed air inlet valve as well as a compressed air outlet valve must 
be installed by the owner, so that the dryer can be installed and maintained in 
a depressurised condition (see also the installation example on page 24). 
  All pipes, couplings, and connections must have the correct diameter and 
match the operating pressure. 
 
 
Hazard caused by exceeding the limit values! 
A safety device must be provided in order to protect against the maximum 
permissible operating pressure from being exceeded.  
The safety device must be installed so that the dryer is reliably protected 
from exceeding the maximum permitted operating pressure even when 
the temperature of the compressed gas increases. 
The data required to meet these preconditions are contained in the technical 
documentation attached in the annex. 
 
 
If the above preconditions are not complied with, a safe operation of the 
dryer cannot be assured. Also, the functionality of the dryer may be 
detrimentally affected.