INSTALLATION
PLUMBING
Cell Installation
The Cell housing must be installed vertically with the inlet and discharge plumbing
positioned such that the water enters and exits the cell chamber at the lowest point of the
vertical cell.
50mm pipe must be plumbed directly onto both ends of the cell with the water flowing in
the direction as indicated by the arrow on the cell housing.
50-40mm reducing bushes will be required for 40mm plumbing.
Do not use barrel unions directly on both sides of the horizontal plumbing that connect to
the cell housing. Unions may loosen and cause the cell to rotate from a vertical upwards
position which will disable the physical ability for the cell to contain a hydrogen gas build
up.
Barrel unions can be used, but must be arranged so that the cell cannot rotate if they are
loosened. For example, if at least one of the unions is on a vertical or perpendicular pipe
leading to the cell.
Positioning the Cell
The cell must be installed on the pool return line, DOWN STREAM of all other equipment
such as the filter, heaters and solar heaters. This is very important in preventing
accumulation of Hydrogen gas as well as corrosion of equipment such as a heat
exchange. Where the cell is installed below pool water level, ensure isolating valves are
installed somewhere either side of the cell, so it can be inspected or removed.