8. Secure the chassis to the ground with the correct fasteners for the location.
9. Trim around the pedestal base to remove any excess rubber from the splash mat.
NOTE: All electrical work must be performed in accordance with the current Electrical
Wiring Regulations.
10. Terminate the supply cable in the appropriate manner and connect to the
pedestal as per the appropriate model number schematic.
11. If required, connect the Ethernet cable to the Communications unit.
12. Make sure all cable connections are secure and have not become loose or
damaged in transit or during installation.
13. Make sure ALL debris is removed from the front and rear halves of the enclosure
and that no debris is present on any of the components.
IMPORTANT NOTE:
It is the responsibility of the installing engineer to satisfy themselves, that all cable
terminations throughout this product are secure and tight and have not become
loose, strained, or disconnected during transit and/or installation.
WARNING: Electrical Power
Make sure it is safe to apply electrical power to the charger.
14. Switch on the overload/fault current devices (main power & LED lamp).
15. Switch ON the power to the unit and test in accordance with the current Electrical
Wiring Regulations.
x Make sure this product has been installed in compliance with the current
Electrical Wiring Regulations (including recommended earthing arrangements).
16. Make sure you are satisfied that the installation is complete and is in a safe
condition.
17. Refit the front panel, taking care not to trap any electrical cables. Secure the panel
with the fixings removed earlier in the process.
Commissioning
If EV Charge.Online is NOT being used, another service provider will be required to
administer smart services.
Commissioning must be performed in accordance with the alternate service providers
instructions.
Commissioning with EVCharge.Online
NOTE: A Smartphone or similar web enabled device with a working internet connection
is required for the next steps.
If this charging point is to be operated via the EVCharge.Online back office:
1. All preliminary tasks listed in the Host’s Guide must have been performed by the
customer (Host) before commissioning can proceed.