6-2 EB 8097 EN
Start-up
Risk of contamination of the process me-
dium through high pressure in the steam
barrier.
A pressure in the steam barrier (steam or
sterile uid) that is higher than the pressure
in the valve itself may affect the process me-
dium inside the valve due to it be mixed with
the steam (or sterile uid).
Î Observe the relevant hygiene regula-
tions.
Before start-up or putting the valve back into
service, make sure the following conditions
are met:
The control valve is properly installed in
the pipeline (see the 'Installation' chap-
ter).
The leak and function tests have been
completed successfully (see the 'Testing
the installed valve' chapter).
The prevailing conditions in the plant
section concerned meet the valve sizing
requirements (see section 'Intended use'
in the 'Safety instructions and measures'
chapter).
Start-up/putting the device back into oper-
ation
1. Allow the valve to cool down or warm up
to reach ambient temperature before
start-up when the ambient temperature
and process medium temperature differ
greatly or the medium properties require
such a measure.
2. Slowly open the shut-off valves in the
pipeline. Slowly opening these valves
prevents a sudden surge in pressure and
high ow velocities which can damage
the valve.
3. Check the valve to ensure it functions
properly.