LED R&D Lab(VD)
43
6. S-Box Installation and Connection
① Installing it in a 19-inch server rack is recommended.
※ When connecting two or more times for the purpose of using multi-link HDR, install it on the ground shielded rack and use it. (SBB-
SNOWJMU model)
② Make sure the air vent is open and not overturned or turned sideways.
③ Exercise caution to ensure that the air vent is not covered by an object. Covered air vent may cause overheating of the product.
④ If installing multiple S-Boxes, make sure there is a gap of at least 1U (44.45 mm) from the product at the top.
⑤ If installing an S-Box onto a wall, make sure there is a gap of at least 10 mm between the wall and the top, bottom and sides of the
product. Make sure there is a gap of at least 50 mm between the cable ports and the wall to ensure proper cable connection.
⑥ Maintain the residual heat inside the rack at a temperature below 35°C.
⑦ Exercise caution to ensure that no liquid enters the air vent of the product.
• Precautions for installing S-Box
SBB-SNOWJAU / SBB-SNOWJMU