1) For the lowest row, install cabinets in the left-to-right direction.
2) After installing one row of sets is completed, connect signal and power cables between the cabinets.
After installation of one row of sets and signal connection are completed, turn on the sets to check that the
installation has been done correctly before installing the next row sets.
3) From the second row, install cabinets vertically (left→right).
1) First row: Install in the
left → right direction
Check that there is no
significant height
difference between
modules inside cabinets.
After connecting all signal/power
cables between the sets, make
sure you turn on the sets to
check that the display on one row
works properly before installing
the upper row.
2) Connect signal/power
cables between the sets
Check that there is no
significant front/back height
difference between cabinets
and the LEDs are arranged in
a straight line.
3) From second row: Install
cabinets and connect
cables vertically
4) Use the same method
to install cabinets and
connect cables
vertically.
8. Power and Cable Connection
8-3. Cabinet Installation Direction (Full Front Installation)