S&C Instruction Sheet 695-535 7
Shipping and Handling
Examine the shipment for external evidence of damage as soon after receipt as possible,
preferable before the carrier departs. Check the bill of lading to make sure the listed
shipping packages are present.
If there is visible loss and/or damage:
1. Notify the delivering carrier immediately.
2. Ask for a carrier inspection.
3. Note condition of shipment on all copies of the delivery receipt.
4. File a claim with the carrier.
If concealed damaged is discovered:
1. Notify the delivering carrier within 15 days of receipt of shipment.
2. Ask for a carrier inspection.
3. File a claim with the carrier.
Notify S&C Electric Company in all instances of loss and/or damage.
The overcurrent control for the S&C Vista SD Underground Distribution System is
housed in a enclosure mounted on the operation side of the switchgear. The enclosure
is fully submersible.
DANGER
Never disconnect the current transformer secondary circuits without de-energizing
the switchgear. Hazardous voltage is present and will shock, burn, or cause death.
NOTICE
S&C does not recommend removing the submersible S&C Overcurrent
Control used in Vista SD Underground Distribution Switchgear from its enclosure
for workbench programming. Opening the submersible enclosure may damage the
sealing gasket. Contact your local S&C Sales Office or the S&C Global Support
and Monitoring Center at 1-888-762-1100 (or 1-773-338-1000 outside the U.S.) for
more information.
Inspection
Packaging
Handling