S&C Instruction Sheet 695-535 43
Performing a Trip Test
Trip tests can only be performed with the Admin login to the overcurrent control. When
a Trip test is performed, the overcurrent control will send a signal to actuate the trip
solenoids in the switchgear, tripping the fault interrupters and opening the circuit.
NOTICE
Test tripping the overcurrent control will open the fault interrupter and may cause
unplanned loss of load.
The Test Trip menu contains eight trip modes:
Trip Mode: Three-Phase, Interrupter 1, All Phases
Trip Mode: Three-Phase, Interrupter 2, All Phases
Trip Mode: Single-Phase, Interrupter 1, Phase A
Trip Mode: Single-Phase, Interrupter 1, Phase B
Trip Mode: Single-Phase, Interrupter 1, Phase C
Trip Mode: Single-Phase, Interrupter 2, Phase A
Trip Mode: Single-Phase, Interrupter 2, Phase B
Trip Mode: Single-Phase, Interrupter 2, Phase C
To test trip the Vista SD Underground Distribution Switchgear:
STEP 1. Click on the Test Trip tab and select the Test Trip menu. From the drop-down
menu, select the trip mode desired for your conguration of switchgear. Vista
SD Underground Distribution is only available in the Three-Phase trip mode.
See Figure 31. A conrmation menu will appear asking “Test Trip Command to
be Issued. OK to continue?
Figure 31. The Test Trip Menu.
STEP 2. Click on the Execute button to proceed with the Trip test. Click on the Cancel
button to return to the Test Trip menu.