EasyManua.ls Logo

Siemens 8DA10 Series - Page 162

Siemens 8DA10 Series
214 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Operation
162/214 Revision 11 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DA10 • 861-9601.9
1
Initial situation
2
Push the interrogation lever downwards.
3
Push the control gate to the right.
4
Switch the three-position disconnector to READY-
TO-EARTH position (insert the operating lever for
the READY-TO-EARTH function and turn 180°
clockwise).
5
Remove the operating lever for the READY-TO-
EARTH function.
The interrogation lever and the control gate return to
their initial position.
6
Close the circuit-breaker to earth the feeder.
Padlock the "feeder earthed“ locking device.

Table of Contents

Related product manuals