Operation
162/214 Revision 11 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DA10 • 861-9601.9
1
Initial situation
2
Push the interrogation lever downwards.
3
Push the control gate to the right.
4
Switch the three-position disconnector to READY-
TO-EARTH position (insert the operating lever for
the READY-TO-EARTH function and turn 180°
clockwise).
5
Remove the operating lever for the READY-TO-
EARTH function.
The interrogation lever and the control gate return to
their initial position.
6
Close the circuit-breaker to earth the feeder.
Padlock the "feeder earthed“ locking device.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 8DA10 Series and is the answer not in the manual?

Siemens 8DA10 Series Specifications

General IconGeneral
BrandSiemens
Model8DA10 Series
CategoryCircuit breakers
LanguageEnglish

Related product manuals