500-8067.9 * INSTALLATION AND OPERATING INSTRUCTIONS 8DJH * Revision 03 91
Installation
Ö Mount the cross member and the cable compartment cover.
Cable installation in
switchgear with pressure
absorber up to 21 kA
Fig. 63: Inserting the front floor cover and the rubber sleeves (switchgear up to 16 kA)
a
Rubber sleeves for cable entry (diameter 70 mm)
d
Front floor cover
s
If required, use rubber sleeves for control cables (diameter 56 mm) /
screened cable plugs
Fig. 64: Switchgear with pressure absorber up to 21 kA
a
Cable compartment cover
s
Cross member
d
Front plate of
the pressure absorber

Table of Contents