Description of the SCALANCE W78x
Operating Instructions SCALANCE W78x
40
3.3.3 Assembling an IE FC TP Standard Cable 4 x 2 GP or IE FC TP
Flexible Cable 4 x 2 GP with an IE IP 67 Hybrid Connector
Remove the two inner shells of the
universal sealing ring to adapt it to
the diameter of the hybrid cable.
Push the bushing, washer, adapted
universal sealing ring and the
housing over the cable jacket.
Remove the following lengths of
cable jacket and shield braid:
25 mm for the power leads.
30 mm for the data leads.
To achieve good shielding, the shield
braid must be alt least 30 mm long.
Arrange the data leads according to
the color codes on the splice
element. The following table shows
the assignment of the data leads.
Wind the shield braid around the data
leads. As a result, the shielding of the
cable has contact to the shield plate
of the splice element that will be fitted
later.
Contact and color assignment of the
splice element.
C79000-G8976-C184-07